Pressure test at Shanxian

On July 20, 2006 the National Bio Energy Co., Ltd. owned Shanxian biomass boiler successfully passed the boiler pressure test. This major project milestone is met 10 weeks after starting welding pressure parts on site.

BWE has supplied the basic engineering for this 30 MWe boiler that will use wood chips and cotton stalks as fuel. The boiler is situated in Shandong Province, Peoples Republic of China.

Further reading:

Shanxian Biomass Power Plant

Shanxian Biomass Power Plant